2016/10 New SAP C_TPLM22_64: SAP Certified Application Associate – Project System with SAP ERP 6.0 EHP4 Exam Questions Released Today!
1.|2016/10 Latest C_TPLM22_64 Exam Dumps (PDF & VCE) 85Q&As Download:
http://www.braindump2go.com/c-tplm22-64.html
2.|2016/10 Latest C_TPLM22_64 Exam Questions & Answers:
https://1drv.ms/b/s!AvI7wzKf6QBjd2-aL2jOPXb_vpo
QUESTION 10
In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity. How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?
Please choose the correct answer.
A. The system uses the key from the work center
B. Costing key is considered
C. The costs are distributed evenly over the earliest dates in the activity
D. System uses valuation variant
Answer: A
QUESTION 11
Among the various functions provided by progress tracking that simplify data entry and analysis which function allows you to go the master data display for objects that are underlined? Please choose the correct answer.
A. Copying dates
B. Subitems
C. Mass change of scenarios
D. Hotspots
Answer: D
QUESTION 12
In progress tracking what are the different ways of assigning the dates of events that are assigned to network components while evaluation?
There are 3 correct answers to this question.
A. Using BADIs
B. Generation and assignment of a new event
C. Direct assignment of a new event
D. Direct assignment of a standard event
Answer: ABD
QUESTION 13
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element. Which of the following costs can be planned? There are 3 correct answers to this question.
A. Each material
B. Cost element level
C. Internal service
D. Each internal activity
Answer: ABD
QUESTION 14
Which transaction along with suitable selection criteria allows you to specify which networks and sub networks are to be taken into account as part of overall network scheduling? Please choose the correct answer.
A. CN22N
B. CN24N
C. CN21N
D. CN23N
Answer: B
QUESTION 15
What is the flag used for WBS elements for which you want to plan costs?
Please choose the correct answer.
A. Billing elements
B. Assignment elements
C. Planning elements
D. Revenue elements
Answer: C
QUESTION 16
Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network? Please choose the correct answer.
A. Stock item
B. Non-stock item
C. Network item
D. Procurement item
Answer: B
!!!RECOMMEND!!!
1.Braindump2go|2016/10 Latest C_TPLM22_64 Exam Dumps (PDF & VCE) 85Q&As Download:
http://www.braindump2go.com/c-tplm22-64.html
2.Braindump2go|2016/10 Latest C_TPLM22_64 Exam Questions & Answers:
https://1drv.ms/b/s!AvI7wzKf6QBjd2-aL2jOPXb_vpo