The Microsoft 70-177 Practice Exam is a very hard exam to successfully pass your exam.Here you will find Free Braindump2go Microsoft Practice Sample Exam Test Questions that will help you prepare in passing the 70-177 exam.Braindump2go Guarantees you 100% PASS exam 70-177
Vendor: Microsoft
Exam Code: 70-177
Exam Name: TS: Microsoft Project Server 2010, Configuring
Keywords: 70-177 Exam Dumps,70-177 Practice Tests,70-177 Practice Exams,70-177 Exam Questions,70-177 PDF,70-177 VCE Free,70-177 Book,70-177 E-Book,70-177 Study Guide,70-177 Braindump,70-177 Prep Guide
QUESTION 61
You have a Project Server 2010 environment.
You need to assign a project to the Help Desk resources and allow these resources to self-assign which tasks to work on.
What should you do?
A. Create and populate the Team Name Lookup Table with the name of the Help Desk team.
Assign the Help Desk resources to that team.
Then assign all tasks to a Team Assignment Pool resource for that team.
B. Create and populate the Team Name Lookup Table with the name of the Help Desk team.
Assign a generic resource as the Team Assignment Pool resource for that team.
Then change all the Assignment Owner fields for the Help Desk resources to that generic resource.
C. Create a department named Help Desk.
Assign the Help Desk resources to that department.
Then publish the project to that department.
D. Create a department named Help Desk.
Assign a generic resource to that department.
Then change all the Assignment Owner fields for the Help Desk resources to that generic resource.
Answer: A
QUESTION 62
You have a Project Server 2010 environment.
You deploy two workflows-one for small projects and one for large projects.
You need to associate the workflows with the correct projects.
What should you create for each workflow?
A. a project details page
B. an enterprise custom field
C. an enterprise project type
D. an enterprise project template
Answer: C
QUESTION 63
You have a Project Server 2010 environment.
A developer creates, tests, and deploys a workflow to the farm.
You need to make the workflow available in Project Web App (PWA).
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. In Project Web App (PWA), select Site Settings, select Workflow settings, and then select
Add a workflow.
B. In Project Web App (PWA), select Site Settings, select Manage site features, and then
activate the workflow.
C. In SharePoint Central Administration, select Manage farm features, and then select Activate Global Web Parts.
D. In SharePoint Central Administration, select Application Management, and then create a site collection for the workflow.
Answer: AB
QUESTION 64
You have a Project Server 2010 environment.
Portfolio managers delete rejected proposed projects once a month.
You need to configure Project Server 2010 to retain electronic copies of the rejected proposed projects for future review.
What should you do?
A. Configure the Daily Backup Schedule in Project Web App (PWA).
B. Configure the Project Site Settings in Project Web App (PWA).
C. Create a view on Project Web App (PWA) for rejected proposed projects.
D. Create a category in Project Web App (PWA) and add the rejected proposed projects to the category.
Answer: A
QUESTION 65
You have a Project Server 2010 environment.
A project is checked out to another user.
You need to delete the checkedout project.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. Use the Manage Users tool to deactivate the user.
B. Use the Force Checkin Enterprise Objects tool to check in the project.
C. Use the Delete Enterprise Objects tool to remove the project from the Draft and Published databases.
D. Open the project in Project Professional and delete all resource assignments.
Answer: BC
QUESTION 66
You have a Project Server 2010 environment.
A project manager creates a project plan.
When attempting to update the project plan, the project manager cannot open it with read/write permissions.
You need to ensure that the project manager can open and update the project plan.
What should you do?
A. Add the project manager to the My Organization category.
B. Select the Check in My Projects option in the Project Center.
C. Perform a forced checkin of the project plan.
D. Perform an Administrative Restore of the project.
Answer: C
QUESTION 67
You have a Project Server 2010 environment.
Your company’s CIO is performing an audit of the inactive tasks that project managers have in their project plans.
However, the CIO cannot access inactive tasks in any Data Analysis view.
You need to ensure that the company executives can access inactive tasks in the OLAP cube. What should you do?
A. Include the Flag Status_Task field as a dimension in the cube.
B. Select the Include Inactive Tasks check box in the Database Configuration page for the cube.
C. Select the (Select All) check box for Built-in Measures in the Database Configuration page
for the cube.
D. Create a custom OLAP cube with a custom field named Inactive.
Answer: B
QUESTION 68
You have a Project Server 2010 environment.
You delete a project named Project A from the Project Server database, but you do not delete the Project Site for this project.
You create a new project named Project B and publish it to the Project Server database.
You need to use Project A’s Project Site for Project B.
What should you do?
A. Synchronize users for Project
B. B. Rename the Project Site to Project A.
C. Enter the URL of Project B’s Project Site on the Project Sites page.
D. Enter the URL of Project A’s Project Site on the Project Sites page.
Answer: D
QUESTION 69
You have a Project Server 2010 environment.
You need to create a report that displays projects by workflow phase.
What should you do?
A. Create a Project Center view.
B. Create a new OLAP cube.
C. Create a Project view.
D. Create a new workflow.
Answer: A
QUESTION 70
You have a Project Server 2010 environment.
You have a single OLAP cube that your executives are using for data analysis.
The Department lookup table lists Departments A and B.
You need to create a view that shows total project resource costs for Department B, without allowing access to information for Department A.
What should you do?
A. Create a new OLAP cube and set department filters.
B. Create a new OLAP view that filters for Department B.
C. Create a new Portfolio Analysis view that filters for Department B.
D. Create an enterprise custom project field that points to the Department lookup table.
Answer: A
Guaranteed 100% Microsoft 70-177 Exam Pass OR Full Money Back! Braindump2go Provides you the latest 70-177 Dumps PDF & VCE for Instant Download!